NORTH MYRTLE BEACH, S.C. -- The City of North Myrtle Beach is in the process of inspecting and cleaning our ocean outfalls.
On July 4, the City began at 6th Avenue South and remained in place until July 17. On July 18, the Jack-Up Barge was relocated to Main Street and will remain in place for one week. The next three locations include 21st Avenue South, 39th Avenue South, and then 45th Avenue South. It is anticipated that each location will take one week, weather dependent.
While inspecting and cleaning, if deficiencies are found, they are repaired immediately by a diver.
The City conducts these routine inspections and cleanings every five years.
We appreciate the community's understanding and cooperation as we carry out this essential maintenance work.